Renovation Updates
December 2024



November 2024




October 2024
Plans for the parking lot currently include 69 spaces, with adjustments being made to minimize environmental impact. Landscaping plans are also in progress, with site lighting and bus stop benches included. Structural and mechanical updates have moved forward, including approval for an air-cooled chiller, a 30-year roof warranty, and the replacement of an old water heater. On the lower level, the existing boys' restroom will stay, with a new accessible restroom being added.
The district is pursuing several grants, such as the Renew America and Multi-modal Grants, with support from local and state leaders. Funding applications for kitchen equipment and community facilities are also underway. Weekly construction meetings are being held to keep the project on track, and safety remains a top priority, with privacy screens, temporary barriers, and updated signs ensuring restricted access to construction areas.
September 2024
Before the school year began, abatement work in the boiler room and the removal of two decommissioned hot water tanks were completed.
Following this, the exterior walls in the boys' restroom and principal's office on floor 1A, classroom 7 on floor 1B, and classroom 25 on the 2nd floor were demolished and removed. These steps are crucial for integrating the new main entrance addition into the existing building.
Excavation work is now underway. Using an excavator and bobcat, digging down to the building foundation footer has begun. This is a critical step in constructing the new foundation for the addition. In tandem with this, the associated sidewalk was removed, and the district's flagpole was taken down.
To ensure safety during construction, privacy screens have been installed, and appropriate signage is displayed on the construction fencing. Additionally, temporary insulated wall barricades have been placed at the existing main entrance, the ramp to the 2nd floor, and the lower lot stairwell to restrict access to construction zones for students and staff.
August 2024
The abatement work is on track and was completed on Monday, August 12th. This included the Lower Level, 1A, 1B, and the 2nd floor. The scope of this work involved removing asbestos-containing materials (ACM) from floor tiles and mastic in various rooms throughout the school. Temporary flooring has been installed following the abatement process. Additionally, the process of demolishing and removing the hot water tanks in the mechanical room has been completed.
In terms of excavation, insulated drywall partitions have been installed on the 7th and 8th floors of 1B, in classroom 25 on the 2nd floor, and in the boys’ restroom at the main entrance. This preparation is crucial for the upcoming exterior wall demolition, which will pave the way for the new main entrance addition. Exterior wall demolition has been completed, allowing excavation to begin.
We are grateful for the support of Senator Costa and Representative Salisbury, whose assistance has been invaluable in moving this project forward.
Due to the front entrance being under renovation, there are updated procedures for arrival and dismissal to ensure the safety of all students. Information on the updated procedures can be found here.
Additionally, we invite you to join us for a Community Renovation Meeting on Wednesday, September 11, at 6:00 pm. The meeting will be held at Turner Intermediate and streamed online.